Project Details
Work Type Repaving, sidewalk, signing, pavement markings, signalization and lighting
Phase Design
Limits west of Belcher Rd. to east of US 19
Length 1.2 Miles
City
County
Road
Design Cost $1.27M
About

This project will repave a 1.2-mile stretch of SR 686 (Roosevelt Boulevard/East Bay Drive) from west of Belcher Road to the east of US 19 in Pinellas County.

In addition, new bicycle lanes, ADA improvements, upgraded LED lighting, signage, pavement markings, and signalization upgrades will also be included.

This project is in the design phase.

Construction activities are anticipated to begin in the summer of 2025.

 