I-4 Interchange Improvement at SR 566 (Thonotosassa Road A) Exit 19 443317-1-52-01
Project Details
| Work Type | Interchange Improvements |
|---|---|
| Phase | Construction |
| Limits | Thonotosassa Road (SR 566) and I-4 Exit 19 |
| Project Start | September 11, 2024 |
| Length | .596 miles |
| City | |
| County | |
| Road | |
| Estimated Completion | Early 2026 |
| Contractor | Watson Civil Construction, Inc. |
About
This project widened SR 566 (Thonotosassa Road) from two to four lanes between the I-4 ramps, added a new northbound right turn lane onto eastbound I-4 entrance ramp, and installed a new traffic signal at the base of the off ramp from westbound I-4.
Construction activities are expected to finish in early 2026.
View Factsheet
Contact Information
| Project Information |
|---|
|
Maricelle Venegas
813-975-6204
Maricelle.Venegas@dot.state.fl.us
|
| Media Contact |
|
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
|
Closures
- There are no closures at this time.