Project Details
Work Type Repaving
Phase Construction
Limits from north of Cherry Tree Lane to north of the Pasco County Line
Project Start May 29, 2024
Length 5.7 miles
City
County
Road
Construction Cost $3.6 million
Estimated Completion Early 2025
Contractor Hubbard Construction, Co.
About

This project is repaving US 301 from north of Cherry Tree Lane to the north of the Pasco County Line. 

Construction activities will take place during daytime and nighttime hours. Work requiring lane closures will occur at night from 7 p.m. to 7 a.m.  

Motorists are reminded to use caution when traveling through the work zone and should remain alert for construction workers. 

Construction activities are estimated to finish during early 2025. 

View Factsheet
Contact Information
Project Information
Maricelle Venegas
813-975-6204
Maricelle.Venegas@dot.state.fl.us
Media Contact
Kris Carson
813-975-6060
Kristen.Carson@dot.state.fl.us
Closures
  • US 301 from north of Cherry Tree Lane to the Pasco County line 
    Night lane closures (northbound): Sunday, July 14 through Friday, July 19 nights from 6:30 p.m. to 7 a.m.
    Day lane closures (southbound): Sunday, July 14 through Friday, July 19 from 8:30 a.m. to 4 p.m.